Wednesday, June 17, 2009

Progress Update

So far we've spent about 3.5 million on the project. It averages out to about $7,000 per day. Now that Phase 1 and Phase 2 are underway there are usually about 30 laborers on site each day.

Phase 1: The exterior is about 95% complete. Lots 2+8 will have flooring installed next week.




Phase 2: The framing is 100% complete on the 2 story homes and about 75% on the 3 stories.